Essential safety improvement works will be carried out on the A52, both Southbound and Northbound, from Saxondale Roundabout to New Lane Road. The work includes refreshing road markings, installing central hatching, high friction surfacing, and a vehicle-activated sign near Tithby road junction. These improvements aim to enhance road safety for all users.
The work is scheduled to start on the 8th of January 2024 and is expected to be completed by the 14th of February 2024. It’s important to note that the planned roadworks are subject to change due to weather conditions or unforeseen circumstances.
During this period, full carriageway closures will occur from Monday to Friday between 8pm and 6am, and some weekend road closures are expected, which will be confirmed nearer the time. Fully signed diversion routes will be in place, agreed upon with the Local Authority.
Access to businesses and residences will be maintained wherever possible, and efforts will be made to minimize disturbances and noise. For further information, please see the attached document.